Assessment Year | 2017 |
---|---|
Principal Product | plastic cups |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
113,000
ft2
|
Annual Production | 16,000,000
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,972 | 2,754,180 |
kWh
|
$0.049 |
Electricity Demand | $63,062 | 6,066 |
kW-mo/yr
|
$10.40 |
Electricity Fees | $44,365 | - |
|
- |
TOTAL YEARLY COSTS | $241,399 | |||
RECOMMENDED SAVINGS* | $101,511 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,869 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3113: Make ice during off peak hours for cooling | $53,389 | $312,800 | - |
$37,467
-
kW-mo/yr
|
$15,922 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,953 | $33,615 |
$7,102
144,947
kWh
|
$6,851
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $7,316 | $240 |
$7,316
149,300
kWh
|
- | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,609 | $8,095 |
$3,413
69,643
kWh
|
$1,196
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,512 | $14,280 |
$4,512
92,077
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $4,286 | $9,500 |
$4,286
87,486
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,134 | $1,660 |
$1,711
34,922
kWh
|
$2,423
-
kW-mo/yr
|
- | |
08 | 2.7496: Install partitions to reduce size of conditioned space | $3,893 | $8,040 |
$2,417
49,325
kWh
|
$1,476
-
kW-mo/yr
|
- | |
09 | 2.4221: Install compressor air intakes in coolest locations | $2,238 | $650 |
$1,573
32,099
kWh
|
$665
-
kW-mo/yr
|
- | |
10 | 2.7135: Install occupancy sensors | $1,858 | $177 |
$1,858
37,923
kWh
|
- | - | |
11 | 2.7221: Lower temperature during the winter season and vice-versa | $711 | $120 |
$711
14,500
kWh
|
- | - | |
12 | 2.7135: Install occupancy sensors | $612 | $1,630 |
$612
12,496
kWh
|
- | - | |
TOTAL RECOMMENDED | $101,511 | $390,807 |
$35,511
724,718
kWh
|
$50,078
-
kW-mo/yr
|
$15,922 | ||
TOTAL IMPLEMENTED | $16,869 | $4,477 |
$13,781
281,240
kWh
|
$3,088
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs