Assessment Year | 2016 |
---|---|
Principal Product | Tobacco Products |
NAICS | 312230: Tobacco Manufacturing |
SIC | 2111: Cigarettes |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 1,800,000
units
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $118,645 | 2,514,000 |
kWh
|
$0.047 |
Electricity Demand | $76,923 | 6,441 |
kW-mo/yr
|
$11.94 |
Electricity Fees | $40,875 | - |
|
- |
TOTAL YEARLY COSTS | $236,444 | |||
RECOMMENDED SAVINGS* | $85,729 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,613 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $39,996 | $70,000 |
$22,870
486,591
kWh
|
$8,026
-
kW-mo/yr
|
$9,100 | |
02 | 2.7293: Install dry sprinkler system or other method to reduce heating requirements | $10,788 | $66,330 |
$7,993
170,072
kWh
|
$2,795
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $8,688 | $320 |
$5,141
109,389
kWh
|
$3,547
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,678 | $27,288 |
$4,329
92,104
kWh
|
$3,349
-
kW-mo/yr
|
- | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,745 | $5,246 |
$2,808
59,745
kWh
|
$1,937
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $3,417 | $650 |
$2,020
42,984
kWh
|
$1,397
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,054 | $9,821 |
$3,054
64,987
kWh
|
- | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,889 | $2,360 |
$1,707
36,312
kWh
|
$1,182
-
kW-mo/yr
|
- | |
09 | 2.4239: Eliminate or reduce compressed air usage | $1,698 | $6,750 |
$981
20,863
kWh
|
$717
-
kW-mo/yr
|
- | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,162 | $1,885 |
$863
18,363
kWh
|
$299
-
kW-mo/yr
|
- | |
11 | 2.7134: Use photocell controls | $776 | $480 |
$776
16,511
kWh
|
- | - | |
12 | 2.7135: Install occupancy sensors | $570 | $795 |
$570
12,133
kWh
|
- | - | |
13 | 2.7447: Install vinyl strip / high speed / air curtain doors | $213 | $352 |
$121
2,580
kWh
|
$92
-
kW-mo/yr
|
- | |
14 | 2.7495: Install replacement doors | $55 | $480 |
$55
1,167
kWh
|
- | - | |
TOTAL RECOMMENDED | $85,729 | $192,757 |
$53,288
1,133,801
kWh
|
$23,341
-
kW-mo/yr
|
$9,100 | ||
TOTAL IMPLEMENTED | $25,613 | $42,071 |
$16,929
360,218
kWh
|
$8,684
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs