Assessment Year | 2015 |
---|---|
Principal Product | Bread |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
78,344
ft2
|
Annual Production | 49,449,670
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $446,543 | 6,650,400 |
kWh
|
$0.067 |
Electricity Demand | $102,410 | 12,801 |
kW-mo/yr
|
$8.00 |
Electricity Fees | $50,057 | - |
|
- |
Natural Gas | $67,286 | 23,523 |
MMBtu
|
$2.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,665 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $81,665 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,740 | $7,980 |
$19,092
284,525
kWh
|
$3,648
-
kW-mo/yr
|
- | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,327 | $16,640 |
$10,349
154,228
kWh
|
$1,978
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,747 | $23,500 |
$7,347
109,500
kWh
|
$2,400
-
kW-mo/yr
|
- | - | - | |
04 | 2.4323: Use optimum size and capacity equipment | $6,899 | $4,691 |
$6,651
99,118
kWh
|
$248
-
kW-mo/yr
|
- | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $5,958 | $7,530 |
$4,998
74,593
kWh
|
$960
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,508 | $1,660 |
$4,865
72,507
kWh
|
$643
-
kW-mo/yr
|
- | - | - | |
07 | 2.3192: Use fossil fuel powered generator during peak demand periods | $4,776 | $1,120 | - | - | - | - | $4,776 | |
08 | 2.4221: Install compressor air intakes in coolest locations | $3,698 | $639 |
$3,106
46,288
kWh
|
$592
-
kW-mo/yr
|
- | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,440 | $40 |
$2,998
44,682
kWh
|
$442
-
kW-mo/yr
|
- | - | - | |
10 | 2.3132: Recharge batteries on during off-peak demand periods | $2,737 | $3,280 | - |
$1,400
-
kW-mo/yr
|
$1,337 | - | - | |
11 | 2.2515: Use optimum thickness insulation | $1,507 | $1,610 | - | - | - |
$1,507
-
MMBtu
|
- | |
12 | 2.7135: Install occupancy sensors | $1,295 | $290 |
$1,295
19,327
kWh
|
- | - | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $574 | $1,400 |
$482
7,188
kWh
|
$92
-
kW-mo/yr
|
- | - | - | |
14 | 2.6231: Utilize controls to operate equipment only when needed | $459 | $90 |
$394
5,865
kWh
|
$65
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $81,665 | $70,470 |
$61,577
917,821
kWh
|
$12,468
-
kW-mo/yr
|
$1,337 |
$1,507
-
MMBtu
|
$4,776 | ||
TOTAL IMPLEMENTED | $81,665 | $70,470 |
$61,577
917,821
kWh
|
$12,468
-
kW-mo/yr
|
$1,337 |
$1,507
-
MMBtu
|
$4,776 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs