ITAC Assessment: MI0277
ITAC logo
ITAC Assessment: MI0277
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Bread
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 112
Plant Area 78,344
ft2
Annual Production 49,449,670
lb
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $446,543 6,650,400
kWh
Electricity Demand $102,410 12,801
kW-mo/yr
Electricity Fees $50,057 -
Natural Gas $67,286 23,523
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $81,665

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $22,740 $7,980 $19,092
284,525
kWh
$3,648
-
kW-mo/yr
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,327 $16,640 $10,349
154,228
kWh
$1,978
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,747 $23,500 $7,347
109,500
kWh
$2,400
-
kW-mo/yr
- - -
04 2.4323: Use optimum size and capacity equipment $6,899 $4,691 $6,651
99,118
kWh
$248
-
kW-mo/yr
- - -
05 2.4239: Eliminate or reduce compressed air usage $5,958 $7,530 $4,998
74,593
kWh
$960
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,508 $1,660 $4,865
72,507
kWh
$643
-
kW-mo/yr
- - -
07 2.3192: Use fossil fuel powered generator during peak demand periods $4,776 $1,120 - - - - $4,776
08 2.4221: Install compressor air intakes in coolest locations $3,698 $639 $3,106
46,288
kWh
$592
-
kW-mo/yr
- - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $3,440 $40 $2,998
44,682
kWh
$442
-
kW-mo/yr
- - -
10 2.3132: Recharge batteries on during off-peak demand periods $2,737 $3,280 - $1,400
-
kW-mo/yr
$1,337 - -
11 2.2515: Use optimum thickness insulation $1,507 $1,610 - - - $1,507
-
MMBtu
-
12 2.7135: Install occupancy sensors $1,295 $290 $1,295
19,327
kWh
- - - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $574 $1,400 $482
7,188
kWh
$92
-
kW-mo/yr
- - -
14 2.6231: Utilize controls to operate equipment only when needed $459 $90 $394
5,865
kWh
$65
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $81,665 $70,470 $61,577
917,821
kWh
$12,468
-
kW-mo/yr
$1,337 $1,507
-
MMBtu
$4,776
TOTAL IMPLEMENTED $81,665 $70,470 $61,577
917,821
kWh
$12,468
-
kW-mo/yr
$1,337 $1,507
-
MMBtu
$4,776
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs