Assessment Year | 2014 |
---|---|
Principal Product | Comercial Printing |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
150,000
ft2
|
Annual Production | 300,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,975 | 4,633,800 |
kWh
|
$0.046 |
Electricity Demand | $186,820 | 15,953 |
kW-mo/yr
|
$11.71 |
Electricity Fees | $20,649 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,847 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,894 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $48,959 | $119,260 |
$34,772
755,914
kWh
|
$14,187
-
kW-mo/yr
|
- | |
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $13,152 | $5,847 |
$9,326
203,850
kWh
|
$3,826
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $11,002 | $11,420 |
$7,814
169,873
kWh
|
$3,188
-
kW-mo/yr
|
- | |
04 | 4.821: Pay bills on time to avoid late fees | $4,107 | $240 | - | - | $4,107 | |
05 | 2.7425: Clean or color roof to reduce solar load | $3,538 | $3,615 |
$2,509
54,855
kWh
|
$1,029
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $3,521 | $580 |
$2,501
54,363
kWh
|
$1,020
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,207 | $4,600 |
$2,271
49,647
kWh
|
$936
-
kW-mo/yr
|
- | |
08 | 2.6218: Turn off equipment when not in use | $3,117 | $1,620 |
$2,239
48,946
kWh
|
$878
-
kW-mo/yr
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,593 | $80 |
$1,914
41,831
kWh
|
$679
-
kW-mo/yr
|
- | |
10 | 2.7111: Reduce illumination to minimum necessary levels | $2,668 | $760 |
$1,895
41,194
kWh
|
$773
-
kW-mo/yr
|
- | |
11 | 2.4221: Install compressor air intakes in coolest locations | $2,665 | $80 |
$1,893
41,375
kWh
|
$772
-
kW-mo/yr
|
- | |
12 | 2.6218: Turn off equipment when not in use | $2,344 | $3,600 |
$1,213
26,362
kWh
|
$1,131
-
kW-mo/yr
|
- | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $986 | $1,660 |
$691
15,092
kWh
|
$295
-
kW-mo/yr
|
- | |
14 | 2.4231: Reduce the pressure of compressed air to the minimum required | $988 | $80 |
$719
15,708
kWh
|
$269
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $102,847 | $153,442 |
$69,757
1,519,010
kWh
|
$28,983
-
kW-mo/yr
|
$4,107 | ||
TOTAL IMPLEMENTED | $33,894 | $15,782 |
$20,766
453,436
kWh
|
$9,021
-
kW-mo/yr
|
$4,107 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs