ITAC Assessment: MI0261
ITAC logo
ITAC Assessment: MI0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Comercial Printing
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 150,000
ft2
Annual Production 300,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,975 4,633,800
kWh
Electricity Demand $186,820 15,953
kW-mo/yr
Electricity Fees $20,649 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,894

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.2622: Replace existing chiller with high efficiency model $48,959 $119,260 $34,772
755,914
kWh
$14,187
-
kW-mo/yr
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $13,152 $5,847 $9,326
203,850
kWh
$3,826
-
kW-mo/yr
-
03 2.2511: Insulate bare equipment $11,002 $11,420 $7,814
169,873
kWh
$3,188
-
kW-mo/yr
-
04 4.821: Pay bills on time to avoid late fees $4,107 $240 - - $4,107
05 2.7425: Clean or color roof to reduce solar load $3,538 $3,615 $2,509
54,855
kWh
$1,029
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $3,521 $580 $2,501
54,363
kWh
$1,020
-
kW-mo/yr
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,207 $4,600 $2,271
49,647
kWh
$936
-
kW-mo/yr
-
08 2.6218: Turn off equipment when not in use $3,117 $1,620 $2,239
48,946
kWh
$878
-
kW-mo/yr
-
09 2.4231: Reduce the pressure of compressed air to the minimum required $2,593 $80 $1,914
41,831
kWh
$679
-
kW-mo/yr
-
10 2.7111: Reduce illumination to minimum necessary levels $2,668 $760 $1,895
41,194
kWh
$773
-
kW-mo/yr
-
11 2.4221: Install compressor air intakes in coolest locations $2,665 $80 $1,893
41,375
kWh
$772
-
kW-mo/yr
-
12 2.6218: Turn off equipment when not in use $2,344 $3,600 $1,213
26,362
kWh
$1,131
-
kW-mo/yr
-
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $986 $1,660 $691
15,092
kWh
$295
-
kW-mo/yr
-
14 2.4231: Reduce the pressure of compressed air to the minimum required $988 $80 $719
15,708
kWh
$269
-
kW-mo/yr
-
TOTAL RECOMMENDED $102,847 $153,442 $69,757
1,519,010
kWh
$28,983
-
kW-mo/yr
$4,107
TOTAL IMPLEMENTED $33,894 $15,782 $20,766
453,436
kWh
$9,021
-
kW-mo/yr
$4,107
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs