ITAC Assessment: MI0210
ITAC logo
ITAC Assessment: MI0210
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Fruit Juice
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $100
M
to 500
M
# of Employees 740
Plant Area 1,000,000
ft2
Annual Production 80,000
Tgal
Production Hrs. Annual 8,568
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,666,822 77,902,497
kWh
Electricity Demand $173,576 134,837
kW-mo/yr
Natural Gas $3,550,432 674,530
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $258,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,606

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $64,568 $175,700 $62,955
912,388
kWh
$1,613
-
kW-mo/yr
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $39,559 $7,338 $38,190
553,480
kWh
$1,369
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $24,805 $1,320 $23,727
343,875
kWh
$1,078
-
kW-mo/yr
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $20,342 $1,350 - - $20,342
-
MMBtu
05 2.2414: Use waste heat from hot flue gases to preheat $18,730 $26,000 - - $18,730
-
MMBtu
06 2.7425: Clean or color roof to reduce solar load $18,125 $133,000 $15,370
222,754
kWh
$2,755
-
kW-mo/yr
-
07 2.6231: Utilize controls to operate equipment only when needed $17,851 $20,000 $17,406
252,312
kWh
$445
-
kW-mo/yr
-
08 2.2136: Install / repair insulation on steam lines $16,463 $16,554 - - $16,463
-
MMBtu
09 2.2447: Heat water with exhaust heat $16,131 $30,000 - - $16,131
-
MMBtu
10 2.7231: Use radiant heater for spot heating $8,346 $10,000 $8,138
117,936
kWh
$208
-
kW-mo/yr
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $8,145 $8,889 $7,942
115,097
kWh
$203
-
kW-mo/yr
-
12 2.6218: Turn off equipment when not in use $5,455 $2,425 $5,375
77,903
kWh
$80
-
kW-mo/yr
-
TOTAL RECOMMENDED $258,520 $432,576 $179,103
2,595,745
kWh
$7,751
-
kW-mo/yr
$71,666
-
MMBtu
TOTAL IMPLEMENTED $83,606 $181,634 $60,552
877,565
kWh
$4,324
-
kW-mo/yr
$18,730
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs