| Assessment Year | 2005 |
|---|---|
| Principal Product | Soft drink manufacturing |
| NAICS | 312111: Soft Drink Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $50 M to 100M |
| # of Employees | 130 |
| Plant Area |
180,000
ft2
|
| Annual Production | 16,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $311,704 | 6,278,031 |
kWh
|
$0.050 |
| Electricity Demand | $134,464 | 16,398 |
kW-mo/yr
|
$8.20 |
| Electricity Fees | $47,712 | - |
|
- |
| Natural Gas | $192,944 | 20,166 |
MMBtu
|
$9.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,730 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2622: Replace existing chiller with high efficiency model | $61,700 | $195,000 |
$12,300
246,000
kWh
|
- | - | $40,000 | $9,400 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,798 | $906 |
$5,912
119,071
kWh
|
$1,558
-
kW-mo/yr
|
- | $(-672.0) | - | |
| 03 | 2.2437: Recover waste heat from equipment | $2,613 | $6,960 | - | - |
$2,613
-
MMBtu
|
- | - | |
| 04 | 2.4323: Use optimum size and capacity equipment | $1,062 | $1,536 |
$825
16,618
kWh
|
$237
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,001 | $288 |
$1,001
20,163
kWh
|
- | - | - | - | |
| 06 | 2.7261: Install timers and/or thermostats | $556 | $486 |
$556
11,190
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $73,730 | $205,176 |
$20,594
413,042
kWh
|
$1,795
-
kW-mo/yr
|
$2,613
-
MMBtu
|
$39,328 | $9,400 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs