ITAC Assessment: BD0311
ITAC logo
ITAC Assessment: BD0311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Automotive Bumpers
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 220,000
ft2
Annual Production 1,150,000
pieces
Production Hrs. Annual 5,880
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $740,254 28,907,726
kWh
Electricity Demand $531,540 50,623
kW-mo/yr
Electricity Fees $2,283 -
Natural Gas $1,425,281 152,535
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $198,102 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
01 2.1221: Replace obsolete burners with more efficient ones $135,621 $15,000 - - $135,621
-
MMBtu
- - -
02 2.2437: Recover waste heat from equipment $6,869 $19,000 - - $6,869
-
MMBtu
- - -
03 2.4133: Use most efficient type of electric motors $30,440 $51,950 $16,570
647,280
kWh
$13,870
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $5,646 - $3,292
128,610
kWh
$2,354
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $6,867 $10,230 $3,557
138,945
kWh
$1,920
-
kW-mo/yr
- - - $1,390
06 2.7135: Install occupancy sensors $543 $375 $241
9,426
kWh
$302
-
kW-mo/yr
- - - -
07 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance $6,600 $610 - - - - - $6,600
08 3.3131: Use evaporation to concentrate material $4,860 $8,000 - - - - $4,860
-
gal
-
09 3.4151: Minimize water usage $656 $3,220 - - - $656
-
Tgal
- -
TOTAL RECOMMENDED $198,102 $108,385 $23,660
924,261
kWh
$18,446
-
kW-mo/yr
$142,490
-
MMBtu
$656
-
Tgal
$4,860
-
gal
$7,990
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs