| Assessment Year | 2001 |
|---|---|
| Principal Product | Tube Bending |
| NAICS |
n/a
|
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
71,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,990
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $74,010 | 1,369,578 |
kWh
|
$0.054 |
| Electricity Fees | $1,429 | - |
|
- |
| Natural Gas | $19,252 | 4,106 |
MMBtu
|
$4.69 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $335,059 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,000 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $14,000 | $1,670 | - | - |
$14,000
-
MMBtu
|
- | - | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $4,700 | $1,110 | - |
$4,700
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,939 | $16,000 |
$1,188
21,996
kWh
|
$751
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.3122: Use filtration, centrifuging to remove contaminants | $2,420 | $1,235 | - | - | - |
$2,420
-
gal
|
- | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $312,000 | $150,000 | - | - | - | - | $312,000 | |
| TOTAL RECOMMENDED | $335,059 | $170,015 |
$1,188
21,996
kWh
|
$5,451
-
kW-mo/yr
|
$14,000
-
MMBtu
|
$2,420
-
gal
|
$312,000 | ||
| TOTAL IMPLEMENTED | $14,000 | $1,670 | - | - |
$14,000
-
MMBtu
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs