ITAC Assessment: MI0028
ITAC logo
ITAC Assessment: MI0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Steel shelving
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 62
Plant Area 110,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,160
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,485 985,440
kWh
Electricity Demand $30,216 3,725
kW-mo/yr
Natural Gas $76,523 73,312
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $97,675 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Primary Raw Material Savings
01 3.2123: Convert to high volume low pressure (hvlp) paint guns $61,673 $3,000 n/a - - $61,673
02 2.6231: Utilize controls to operate equipment only when needed $15,305 $930 n/a $15,305
429,608
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,032 $255 n/a $8,032
116,410
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $7,051 $8 n/a $7,051
102,189
kWh
- -
05 3.5131: Recycle white water $5,465 $601 n/a - $5,465
-
Tgal
-
06 2.2514: Cover open tanks $149 $48 n/a $149
2,163
kWh
- -
TOTAL RECOMMENDED $97,675 $4,842 $30,537
650,370
kWh
$5,465
-
Tgal
$61,673
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs