Assessment Year 2000
Principal Product Vinyl Windows
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $50
M
to 100
M
# of Employees 425
Plant Area 100,000
ft2
Annual Production 350,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $256,230 2,847,890
kWh
Electricity Demand $64,512 8,411
kW-mo/yr
Natural Gas $38,250 7,436
MMBtu
LPG $11,782 689
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $445,216 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $434,393

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
01 4.126: Install sensors to detect defects $243,000 $20,108 - - - - $243,000 -
02 4.423: Move product using mechanical means $105,600 $6,000 - - - - $105,600 -
03 4.421: Modify current incentive program $15,000 - - - - - $15,000 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $10,958 $28,528 $10,758
95,252
kWh
$200
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,204 $1,000 $9,204
102,286
kWh
- - - - -
06 4.652: Replace existing equipment with more suitable substitutes $3,402 $4,940 $3,402
37,808
kWh
- - - - -
07 2.4221: Install compressor air intakes in coolest locations $1,619 $1,000 $1,619
18,171
kWh
- - - - -
08 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $1,092 $1,240 - - $1,092
-
MMBtu
- - -
09 4.421: Modify current incentive program $55,341 $30,500 - - - $15,341
-
lb
- $40,000
TOTAL RECOMMENDED $445,216 $93,316 $24,983
253,517
kWh
$200
-
kW-mo/yr
$1,092
-
MMBtu
$15,341
-
lb
$363,600 $40,000
TOTAL IMPLEMENTED $434,393 $91,316 $14,160
133,060
kWh
$200
-
kW-mo/yr
$1,092
-
MMBtu
$15,341
-
lb
$363,600 $40,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs