Assessment Year | 2000 |
---|---|
Principal Product | Vinyl Windows |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $50 M to 100M |
# of Employees | 425 |
Plant Area |
100,000
ft2
|
Annual Production | 350,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $256,230 | 2,847,890 |
kWh
|
$0.090 |
Electricity Demand | $64,512 | 8,411 |
kW-mo/yr
|
$7.67 |
Natural Gas | $38,250 | 7,436 |
MMBtu
|
$5.14 |
LPG | $11,782 | 689 |
MMBtu
|
$17.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $445,216 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $434,393 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.126: Install sensors to detect defects | $243,000 | $20,108 | - | - | - | - | $243,000 | - | |
02 | 4.423: Move product using mechanical means | $105,600 | $6,000 | - | - | - | - | $105,600 | - | |
03 | 4.421: Modify current incentive program | $15,000 | - | - | - | - | - | $15,000 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,958 | $28,528 |
$10,758
95,252
kWh
|
$200
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,204 | $1,000 |
$9,204
102,286
kWh
|
- | - | - | - | - | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $3,402 | $4,940 |
$3,402
37,808
kWh
|
- | - | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,619 | $1,000 |
$1,619
18,171
kWh
|
- | - | - | - | - | |
08 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $1,092 | $1,240 | - | - |
$1,092
-
MMBtu
|
- | - | - | |
09 | 4.421: Modify current incentive program | $55,341 | $30,500 | - | - | - |
$15,341
-
lb
|
- | $40,000 | |
TOTAL RECOMMENDED | $445,216 | $93,316 |
$24,983
253,517
kWh
|
$200
-
kW-mo/yr
|
$1,092
-
MMBtu
|
$15,341
-
lb
|
$363,600 | $40,000 | ||
TOTAL IMPLEMENTED | $434,393 | $91,316 |
$14,160
133,060
kWh
|
$200
-
kW-mo/yr
|
$1,092
-
MMBtu
|
$15,341
-
lb
|
$363,600 | $40,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs