ITAC Assessment: MI0050
ITAC logo
ITAC Assessment: MI0050
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Semiconductor diodes and rectifiers
NAICS
n/a
SIC 3674: Semiconductors and Related Devices
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 40,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,340
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,257 1,788,994
kWh
LPG $33,641 44,530
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $337,624 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Product Savings
01 4.652: Replace existing equipment with more suitable substitutes $173,081 $82,800 - $173,081
02 2.7232: Replace existing hvac unit with high efficiency model $95,397 $66,000 $95,397
1,589,952
kWh
-
03 2.7212: Install or upgrade insulation on hvac distribution systems $53,360 $5,000 $53,360
889,325
kWh
-
04 2.7144: Install spectral reflectors / delamp $10,046 $21,150 $10,046
167,440
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,880 $2 $2,880
48,001
kWh
-
06 2.4224: Upgrade controls on compressors $2,860 $1,338 $2,860
47,669
kWh
-
TOTAL RECOMMENDED $337,624 $176,290 $164,543
2,742,387
kWh
$173,081
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs