Assessment Year | 1998 |
---|---|
Principal Product | Footwear |
NAICS |
n/a
|
SIC | 3143: Men's Footwear, Except Athletic |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
161,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $337,439 | 4,814,771 |
kWh
|
$0.070 |
Electricity Demand | $160,899 | 30,115 |
kW-mo/yr
|
$5.34 |
Electricity Fees | $27,475 | - |
|
- |
LPG | $144 | 7 |
MMBtu
|
$20.57 |
Fuel Oil #2 | $46,538 | 7,979 |
MMBtu
|
$5.83 |
Fuel Oil #4 | $59,077 | 12,891 |
MMBtu
|
$4.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,799 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,304 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.112: Replace old machine with new automatic multi-station tool | $45,000 | $150,000 | - | - | - | - | $45,000 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,132 | $46,836 |
$14,047
200,469
kWh
|
$6,085
-
kW-mo/yr
|
- | - | - | |
03 | 2.3511: Use plant owned transformers or lease transformers | $6,992 | $31,060 | - | - | - | - | $6,992 | |
04 | 4.231: Purchase equipment instead of leasing | $4,542 | $11,495 | - | - | - | - | $4,542 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $2,336 | $300 |
$2,336
33,411
kWh
|
- | - | - | - | |
06 | 2.7291: Reschedule and rearrange multiple-source heating systems | $1,083 | $4,178 | - | - |
$1,083
-
MMBtu
|
- | - | |
07 | 2.2511: Insulate bare equipment | $868 | $858 |
$868
12,309
kWh
|
- | - | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $562 | - |
$562
7,913
kWh
|
- | - | - | - | |
09 | 2.2437: Recover waste heat from equipment | $804 | $1,500 |
$804
40,445
kWh
|
- | - | - | - | |
10 | 2.2511: Insulate bare equipment | $406 | $122 | - | - |
$406
-
MMBtu
|
- | - | |
11 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $74 | - | - | - | - |
$74
-
lb
|
- | |
TOTAL RECOMMENDED | $82,799 | $246,349 |
$18,617
294,547
kWh
|
$6,085
-
kW-mo/yr
|
$1,489
-
MMBtu
|
$74
-
lb
|
$56,534 | ||
TOTAL IMPLEMENTED | $24,304 | $48,116 |
$17,813
254,102
kWh
|
$6,085
-
kW-mo/yr
|
$406
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs