Assessment Year | 1997 |
---|---|
Principal Product | snowplows |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
83,145
ft2
|
Annual Production | 19,000
pieces
|
Production Hrs. Annual | 5,330
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,639 | 3,018,757 |
kWh
|
$0.073 |
Electricity Demand | $87,095 | 8,827 |
kW-mo/yr
|
$9.87 |
Electricity Fees | $6,054 | - |
|
- |
LPG | $218,840 | 29,638 |
MMBtu
|
$7.38 |
Fuel Oil #2 | $19,163 | 2,831 |
MMBtu
|
$6.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,882 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,462 | $33,192 | n/a |
$5,813
82,943
kWh
|
$2,649
-
kW-mo/yr
|
- | - |
02 | 2.2424: Use heat in flue gases to preheat products or materials | $8,031 | $17,000 | n/a | - | - |
$8,031
-
MMBtu
|
- |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,827 | $2,398 | n/a |
$1,827
26,084
kWh
|
- | - | - |
04 | 2.7314: Reduce ventilation air | $1,803 | $6,000 | n/a | - | - |
$1,803
-
MMBtu
|
- |
05 | 2.4221: Install compressor air intakes in coolest locations | $883 | $250 | n/a |
$883
12,603
kWh
|
- | - | - |
06 | 4.231: Purchase equipment instead of leasing | $561 | $1,283 | n/a | - | - | - | $561 |
07 | 2.2511: Insulate bare equipment | $315 | $264 | n/a | - | - |
$315
-
MMBtu
|
- |
TOTAL RECOMMENDED | $21,882 | $60,387 |
$8,523
121,630
kWh
|
$2,649
-
kW-mo/yr
|
$10,149
-
MMBtu
|
$561 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs