| Assessment Year | 2025 |
|---|---|
| Principal Product | Active Ingredients for Herbicides |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 143 |
| Plant Area |
80,000
ft2
|
| Annual Production | 920
ton
|
| Production Hrs. Annual | 5,520
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $6,085,304 | 27,295,562 |
kWh
|
$0.22 |
| Electricity Demand | $427,977 | 93,745 |
kW-mo/yr
|
$4.57 |
| Electricity Fees | $5,400 | - |
|
- |
| TOTAL YEARLY COSTS | $6,518,681 | |||
| RECOMMENDED SAVINGS* | $244,853 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $120,439 | $200 |
$116,450
522,197
kWh
|
$3,989
-
kW-mo/yr
|
- | |
| 02 | 2.7221: Lower temperature during the winter season and vice-versa | $15,745 | $240 |
$15,260
68,430
kWh
|
$485
-
kW-mo/yr
|
- | |
| 03 | 2.9114: Use solar heat to make electricty | $96,937 | $3,200 | - | - | $96,937 | |
| 04 | 2.7135: Install occupancy sensors | $3,143 | $1,775 |
$3,143
14,096
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,443 | $4,136 |
$4,254
19,077
kWh
|
$189
-
kW-mo/yr
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,146 | $12,242 |
$4,018
18,016
kWh
|
$128
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $244,853 | $21,793 |
$143,125
641,816
kWh
|
$4,791
-
kW-mo/yr
|
$96,937 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs