Assessment Year | 1996 |
---|---|
Principal Product | Potato Chips |
NAICS |
n/a
|
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
50,000
ft2
|
Annual Production | 6,500,000
lb
|
Production Hrs. Annual | 1,800
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,530 | 548,945 |
kWh
|
$0.11 |
Electricity Demand | $18,550 | 2,215 |
kW-mo/yr
|
$8.37 |
Electricity Fees | $1,520 | - |
|
- |
LPG | $15,786 | 2,128 |
MMBtu
|
$7.42 |
Fuel Oil #2 | $52,328 | 11,305 |
MMBtu
|
$4.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,007 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $2,928 | - | - | - | - | - | $2,928 | - | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $2,757 | - | - | - |
$2,757
-
MMBtu
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,035 | $9,015 |
$2,551
29,601
kWh
|
$484
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.8123: Pay utility bills on time | $628 | - | - | - | - | - | $628 | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $626 | $1,075 |
$626
9,086
kWh
|
- | - | - | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $397 | $1,000 | - | - | - | - | $397 | - | |
07 | 2.2511: Insulate bare equipment | $236 | $126 | - | - |
$236
-
MMBtu
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $229 | $300 |
$229
3,517
kWh
|
- | - | - | - | - | |
09 | 3.4151: Minimize water usage | $928 | $250 | - | - | - |
$748
-
Tgal
|
- |
$180
-
Tgal
|
|
TOTAL RECOMMENDED | $11,764 | $11,766 |
$3,406
42,204
kWh
|
$484
-
kW-mo/yr
|
$2,993
-
MMBtu
|
$748
-
Tgal
|
$3,953 |
$180
-
Tgal
|
||
TOTAL IMPLEMENTED | $9,007 | $11,766 |
$3,406
42,204
kWh
|
$484
-
kW-mo/yr
|
$236
-
MMBtu
|
$748
-
Tgal
|
$3,953 |
$180
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs