ITAC Assessment: ME0154
ITAC logo
ITAC Assessment: ME0154
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Electrical Components
NAICS
n/a
SIC 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 185,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $393,904 4,395,076
kWh
Fuel Oil #2 $47,641 11,006
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,133 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,252

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $20,883 $50,267 $20,883
231,536
kWh
- - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,527 $1,500 $18,527
205,158
kWh
- - - - - -
03 3.4116: Meter recycled water (to reduce sewer charges) $5,200 $400 - - - $5,200
-
Tgal
- - -
04 4.231: Purchase equipment instead of leasing $11,057 $30,000 - - - - - $11,057 -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,796 $980 $2,796
30,774
kWh
- - - - - -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,537 $1,175 $2,757
58,617
kWh
$(-220.0)
-
MMBtu
- - - - -
07 2.4221: Install compressor air intakes in coolest locations $2,118 $800 $2,118
25,791
kWh
- - - - - -
08 2.1233: Analyze flue gas for proper air/fuel ratio $1,900 $400 - - $1,900
-
MMBtu
- - - -
09 3.4151: Minimize water usage $2,815 $440 $1,820
20,223
kWh
- - $614
-
Tgal
- - $381
-
Tgal
10 3.5212: Regrind, reuse, or sell scrap plastic parts $300 $150 - - - - $300
-
lb
- -
TOTAL RECOMMENDED $68,133 $86,112 $48,901
572,099
kWh
$(-220.0)
-
MMBtu
$1,900
-
MMBtu
$5,814
-
Tgal
$300
-
lb
$11,057 $381
-
Tgal
TOTAL IMPLEMENTED $7,252 $2,015 $4,577
78,840
kWh
$(-220.0)
-
MMBtu
$1,900
-
MMBtu
$614
-
Tgal
- - $381
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs