Assessment Year | 1994 |
---|---|
Principal Product | Woolen fiber |
NAICS |
n/a
|
SIC | 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing) |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
140,000
ft2
|
Annual Production | 18,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $723,958 | 8,692,263 |
kWh
|
$0.083 |
LPG | $5,643 | 922 |
MMBtu
|
$6.12 |
Fuel Oil #2 | $9,402 | 1,434 |
MMBtu
|
$6.56 |
Fuel Oil #6 | $15,985 | 4,706 |
MMBtu
|
$3.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,385 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 4.231: Purchase equipment instead of leasing | $8,107 | $28,250 | - | - | $8,107 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,490 | $250 |
$2,490
29,601
kWh
|
- | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $2,350 | $240 |
$2,350
28,136
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $2,174 | $1,650 |
$2,174
26,084
kWh
|
- | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,333 | $1,768 |
$1,614
16,120
kWh
|
$(-281.0)
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,622 | $800 |
$1,622
19,343
kWh
|
- | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $590 | $800 |
$590
7,034
kWh
|
- | - | |
08 | 2.2511: Insulate bare equipment | $970 | $1,884 |
$970
43,376
kWh
|
- | - | |
TOTAL RECOMMENDED | $19,636 | $35,642 |
$11,810
169,694
kWh
|
$(-281.0)
-
MMBtu
|
$8,107 | ||
TOTAL IMPLEMENTED | $8,385 | $3,858 |
$8,666
100,234
kWh
|
$(-281.0)
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs