| Assessment Year | 1986 |
|---|---|
| Principal Product | CANDLES |
| NAICS |
n/a
|
| SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 110 |
| Plant Area |
n/a
|
| Annual Production | 2,250,000
lb
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $37,370 | 509,965 |
kWh
|
$0.073 |
| LPG | $10,342 | 1,128 |
MMBtu
|
$9.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $730 | $85 |
$730
9,965
kWh
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $901 | $961 |
$1,933
26,377
kWh
|
$(-1,032.0)
-
MMBtu
|
- | |
| 03 | 2.2514: Cover open tanks | $1,330 | $1,239 | - |
$1,330
-
MMBtu
|
- | |
| 04 | 2.8114: Change rate schedules or other changes in utility service | $410 | $191 | - | - | $410 | |
| TOTAL RECOMMENDED | $3,371 | $2,476 |
$2,663
36,342
kWh
|
$298
-
MMBtu
|
$410 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs