Assessment Year | 1999 |
---|---|
Principal Product | Foam and plastic packaging materials |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
150,000
ft2
|
Annual Production | 1,500,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $347,958 | 5,668,816 |
kWh
|
$0.061 |
Electricity Demand | $162,094 | 11,774 |
kW-mo/yr
|
$13.77 |
Electricity Fees | $17,806 | - |
|
- |
Natural Gas | $244,387 | 67,384 |
MMBtu
|
$3.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,695 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $680 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $30,798 | $50,000 |
$26,280
447,538
kWh
|
$10,913
-
kW-mo/yr
|
$(-6,395.0)
-
MMBtu
|
- | |
02 | 2.3212: Optimize plant power factor | $3,519 | $11,400 | - |
$3,519
-
kW-mo/yr
|
- | - | |
03 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $2,232 | $7,614 |
$(-447.0)
(-7,620)
kWh
|
$(-571.0)
-
kW-mo/yr
|
$3,250
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,084 | $3,400 |
$1,084
18,464
kWh
|
- | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $680 | - |
$680
20,223
kWh
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $654 | $985 |
$654
11,137
kWh
|
- | - | - | |
07 | 3.4116: Meter recycled water (to reduce sewer charges) | $500 | $2,675 | - | - | - |
$500
-
Tgal
|
|
08 | 2.6122: Adjust vents to minimize energy use | $228 | $600 | - | - |
$228
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $39,695 | $76,674 |
$28,251
489,742
kWh
|
$13,861
-
kW-mo/yr
|
$(-2,917.0)
-
MMBtu
|
$500
-
Tgal
|
||
TOTAL IMPLEMENTED | $680 | - |
$680
20,223
kWh
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs