ITAC Assessment: MA0451
ITAC logo
ITAC Assessment: MA0451
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Foam and plastic packaging materials
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 150,000
ft2
Annual Production 1,500,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $347,958 5,668,816
kWh
Electricity Demand $162,094 11,774
kW-mo/yr
Electricity Fees $17,806 -
Natural Gas $244,387 67,384
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,695 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $680

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $30,798 $50,000 $26,280
447,538
kWh
$10,913
-
kW-mo/yr
$(-6,395.0)
-
MMBtu
-
02 2.3212: Optimize plant power factor $3,519 $11,400 - $3,519
-
kW-mo/yr
- -
03 2.2426: Use waste heat from flue gases to heat space conditioning air $2,232 $7,614 $(-447.0)
(-7,620)
kWh
$(-571.0)
-
kW-mo/yr
$3,250
-
MMBtu
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,084 $3,400 $1,084
18,464
kWh
- - -
05 2.6231: Utilize controls to operate equipment only when needed $680 - $680
20,223
kWh
- - -
06 2.4221: Install compressor air intakes in coolest locations $654 $985 $654
11,137
kWh
- - -
07 3.4116: Meter recycled water (to reduce sewer charges) $500 $2,675 - - - $500
-
Tgal
08 2.6122: Adjust vents to minimize energy use $228 $600 - - $228
-
MMBtu
-
TOTAL RECOMMENDED $39,695 $76,674 $28,251
489,742
kWh
$13,861
-
kW-mo/yr
$(-2,917.0)
-
MMBtu
$500
-
Tgal
TOTAL IMPLEMENTED $680 - $680
20,223
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs