| Assessment Year | 1999 |
|---|---|
| Principal Product | Cargo Containers, Kayaks |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
202,000
ft2
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $144,557 | 3,845,838 |
kWh
|
$0.038 |
| Electricity Demand | $152,801 | 11,913 |
kW-mo/yr
|
$12.83 |
| Electricity Fees | $63,756 | - |
|
- |
| Natural Gas | $213,160 | 34,608 |
MMBtu
|
$6.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,878 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,195 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,407 | $19,500 |
$6,921
173,212
kWh
|
$2,486
-
kW-mo/yr
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,131 | $4,925 | - |
$2,131
-
kW-mo/yr
|
- | |
| 03 | 2.4237: Substitute compressed air cooling with water or air cooling | $1,511 | $2,500 |
$1,511
34,291
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,321 | $45,420 |
$7,849
181,125
kWh
|
$4,472
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $591 | $120 |
$591
13,482
kWh
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $504 | $455 |
$504
12,603
kWh
|
- | - | |
| 07 | 2.7261: Install timers and/or thermostats | $473 | $748 | - | - |
$473
-
MMBtu
|
|
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $940 | $5,925 |
$940
23,447
kWh
|
- | - | |
| TOTAL RECOMMENDED | $27,878 | $79,593 |
$18,316
438,160
kWh
|
$9,089
-
kW-mo/yr
|
$473
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,195 | $5,793 |
$591
13,482
kWh
|
$2,131
-
kW-mo/yr
|
$473
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs