Assessment Year | 1998 |
---|---|
Principal Product | screen printing |
NAICS |
n/a
|
SIC | 2261: Finishers of Broadwoven Fabrics of Cotton |
Sales Range | $10 M to 50M |
# of Employees | 126 |
Plant Area |
250,000
ft2
|
Annual Production | 156,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,086 | 3,568,875 |
kWh
|
$0.063 |
Electricity Demand | $65,027 | 9,746 |
kW-mo/yr
|
$6.67 |
Natural Gas | $289,854 | 55,908 |
MMBtu
|
$5.18 |
Fuel Oil #6 | $23,616 | 7,808 |
MMBtu
|
$3.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $143,682 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,799 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $99,832 | $87,100 | - | - |
$99,832
-
MMBtu
|
- | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,625 | $8,625 |
$7,625
91,442
kWh
|
- | - | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,188 | $1,000 |
$2,664
31,946
kWh
|
- | - |
$(-476.0)
-
MMBtu
|
- | - | - | |
04 | 3.4145: Use magnetic technology to treat water | $2,939 | $5,520 | - | - | - | - |
$2,939
-
gal
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,735 | $100 |
$1,735
20,809
kWh
|
- | - | - | - | - | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,487 | $2,675 | - | - | - | - | - | $1,487 | - | |
07 | 2.2511: Insulate bare equipment | $644 | $513 | - | - | - |
$644
-
MMBtu
|
- | - | - | |
08 | 3.3128: Utilize other methods to remove contaminants | $27,232 | $250,000 |
$37,320
447,538
kWh
|
$5,074
-
kW-mo/yr
|
$(-24,399.0)
-
MMBtu
|
- | - | - |
$9,237
-
Tgal
|
|
TOTAL RECOMMENDED | $143,682 | $355,533 |
$49,344
591,735
kWh
|
$5,074
-
kW-mo/yr
|
$75,433
-
MMBtu
|
$168
-
MMBtu
|
$2,939
-
gal
|
$1,487 |
$9,237
-
Tgal
|
||
TOTAL IMPLEMENTED | $31,799 | $251,613 |
$41,719
500,293
kWh
|
$5,074
-
kW-mo/yr
|
$(-24,399.0)
-
MMBtu
|
$168
-
MMBtu
|
- | - |
$9,237
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs