Assessment Year | 1995 |
---|---|
Principal Product | Metal Stampings |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 299 |
Plant Area |
110,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 5,380
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $388,564 | 3,404,748 |
kWh
|
$0.11 |
Natural Gas | $26,676 | 3,210 |
MMBtu
|
$8.31 |
Fuel Oil #2 | $3,365 | 785 |
MMBtu
|
$4.29 |
Fuel Oil #4 | $4,745 | 1,195 |
MMBtu
|
$3.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,170 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,047 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Water Disposal Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $18,981 | $7,000 | - |
$11,689
-
MMBtu
|
$3,124
-
MMBtu
|
$4,168
-
MMBtu
|
- | - | |
02 | 2.1332: Convert combustion equipment to burn natural gas | $15,250 | $28,000 |
$19,394
125,147
kWh
|
$(-4,144.0)
-
MMBtu
|
- | - | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $6,705 | $630 |
$6,705
77,960
kWh
|
- | - | - | - | - | |
04 | 2.2511: Insulate bare equipment | $1,806 | $870 |
$1,806
17,878
kWh
|
- | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,260 | $500 |
$1,260
14,654
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,118 | $2,813 |
$1,118
10,551
kWh
|
- | - | - | - | - | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $1,050 | $400 |
$(-212.0)
(-2,052)
kWh
|
- | - | - |
$901
-
Tgal
|
$361
-
Tgal
|
|
TOTAL RECOMMENDED | $46,170 | $40,213 |
$30,071
244,138
kWh
|
$7,545
-
MMBtu
|
$3,124
-
MMBtu
|
$4,168
-
MMBtu
|
$901
-
Tgal
|
$361
-
Tgal
|
||
TOTAL IMPLEMENTED | $22,047 | $8,370 |
$3,066
32,532
kWh
|
$11,689
-
MMBtu
|
$3,124
-
MMBtu
|
$4,168
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Water Disposal Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs