ITAC Assessment: MA0251
ITAC logo
ITAC Assessment: MA0251
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product HEAT TREATED STEEL/ALLOY
NAICS
n/a
SIC 3398: Metal Heat Treating
Sales Range $1
M
to 5
M
# of Employees 22
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,600
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,690 1,155,920
kWh
Natural Gas $80,998 12,455
MMBtu
LPG $6,630 750
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,632 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,295

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings
01 2.8113: Purchase gas directly from a contract gas supplier $15,064 $40,000 - $21,694
-
MMBtu
$(-6,630.0)
-
MMBtu
02 2.2511: Insulate bare equipment $9,500 $1,316 $9,500
91,735
kWh
- -
03 2.4322: Use or replace with energy efficient substitutes $5,623 $2,472 - $5,623
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $2,191 $4,450 - $2,191
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,099 $2,050 - $1,099
-
MMBtu
-
06 2.4239: Eliminate or reduce compressed air usage $1,639 $500 $1,639
15,826
kWh
- -
07 2.6232: Install set-back timers $273 $90 $273
2,638
kWh
- -
08 2.4221: Install compressor air intakes in coolest locations $243 $300 $243
2,345
kWh
- -
TOTAL RECOMMENDED $35,632 $51,178 $11,655
112,544
kWh
$30,607
-
MMBtu
$(-6,630.0)
-
MMBtu
TOTAL IMPLEMENTED $20,295 $11,088 $11,382
109,906
kWh
$8,913
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs