Assessment Year | 1992 |
---|---|
Principal Product | HEAT TREATED STEEL/ALLOY |
NAICS |
n/a
|
SIC | 3398: Metal Heat Treating |
Sales Range | $1 M to 5M |
# of Employees | 22 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,690 | 1,155,920 |
kWh
|
$0.10 |
Natural Gas | $80,998 | 12,455 |
MMBtu
|
$6.50 |
LPG | $6,630 | 750 |
MMBtu
|
$8.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,632 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,295 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $15,064 | $40,000 | - |
$21,694
-
MMBtu
|
$(-6,630.0)
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $9,500 | $1,316 |
$9,500
91,735
kWh
|
- | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $5,623 | $2,472 | - |
$5,623
-
MMBtu
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $2,191 | $4,450 | - |
$2,191
-
MMBtu
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,099 | $2,050 | - |
$1,099
-
MMBtu
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,639 | $500 |
$1,639
15,826
kWh
|
- | - | |
07 | 2.6232: Install set-back timers | $273 | $90 |
$273
2,638
kWh
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $243 | $300 |
$243
2,345
kWh
|
- | - | |
TOTAL RECOMMENDED | $35,632 | $51,178 |
$11,655
112,544
kWh
|
$30,607
-
MMBtu
|
$(-6,630.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $20,295 | $11,088 |
$11,382
109,906
kWh
|
$8,913
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs