| Assessment Year | 1991 |
|---|---|
| Principal Product | PLASTIC CLOSURE & SHEETS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 48 |
| Plant Area |
n/a
|
| Annual Production | 6,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $343,637 | 4,400,645 |
kWh
|
$0.078 |
| Natural Gas | $8,213 | 1,182 |
MMBtu
|
$6.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,568 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,568 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,099 | $2,649 |
$1,099
14,068
kWh
|
- | |
| 02 | 2.2511: Insulate bare equipment | $3,090 | $3,593 |
$3,090
39,566
kWh
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,737 | $9,055 |
$7,737
99,062
kWh
|
- | |
| 04 | 2.7122: Disconnect ballasts | $1,580 | $1,875 |
$1,580
20,223
kWh
|
- | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $4,665 | $5,000 |
$4,665
59,789
kWh
|
- | |
| 06 | 2.6232: Install set-back timers | $393 | $161 |
$393
4,982
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $14,146 | $79,350 |
$14,146
181,125
kWh
|
- | |
| 09 | 2.3212: Optimize plant power factor | $6,858 | - |
$3,049
38,980
kWh
|
$3,809 | |
| TOTAL RECOMMENDED | $39,568 | $101,683 |
$35,759
457,795
kWh
|
$3,809 | ||
| TOTAL IMPLEMENTED | $39,568 | $101,683 |
$35,759
457,795
kWh
|
$3,809 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs