ITAC Assessment: MA0212
ITAC logo
ITAC Assessment: MA0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PLASTIC CLOSURE & SHEETS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 48
Plant Area
n/a
Annual Production 6,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $343,637 4,400,645
kWh
Natural Gas $8,213 1,182
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,568 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,568

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $1,099 $2,649 $1,099
14,068
kWh
-
02 2.2511: Insulate bare equipment $3,090 $3,593 $3,090
39,566
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,737 $9,055 $7,737
99,062
kWh
-
04 2.7122: Disconnect ballasts $1,580 $1,875 $1,580
20,223
kWh
-
05 2.7111: Reduce illumination to minimum necessary levels $4,665 $5,000 $4,665
59,789
kWh
-
06 2.6232: Install set-back timers $393 $161 $393
4,982
kWh
-
07 2.4133: Use most efficient type of electric motors $14,146 $79,350 $14,146
181,125
kWh
-
09 2.3212: Optimize plant power factor $6,858 - $3,049
38,980
kWh
$3,809
TOTAL RECOMMENDED $39,568 $101,683 $35,759
457,795
kWh
$3,809
TOTAL IMPLEMENTED $39,568 $101,683 $35,759
457,795
kWh
$3,809
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs