ITAC Assessment: MA0205
ITAC logo
ITAC Assessment: MA0205
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product CUSTOM BINDERS
NAICS
n/a
SIC 2782: Blankbooks, Looseleaf Binders and Devices
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 5,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $208,124 2,645,662
kWh
Other Energy $94,232 14,284
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,001 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #4 Savings Other Energy Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,259 $13,297 $4,259
54,220
kWh
- -
02 2.6232: Install set-back timers $2,448 $161 $2,448
31,067
kWh
- -
03 2.7261: Install timers and/or thermostats $7,115 $4,000 - - $7,115
-
MMBtu
04 2.1392: Replace purchased steam with other energy source $15,928 - - $(-78,304.0)
-
MMBtu
$94,232
-
MMBtu
05 2.6241: Reduce temperature of process equipment when on standby $614 $897 - - $614
-
MMBtu
06 2.6231: Utilize controls to operate equipment only when needed $1,637 - $1,637
20,809
kWh
- -
TOTAL RECOMMENDED $32,001 $18,355 $8,344
106,096
kWh
$(-78,304.0)
-
MMBtu
$101,961
-
MMBtu
TOTAL IMPLEMENTED $32,001 $18,355 $8,344
106,096
kWh
$(-78,304.0)
-
MMBtu
$101,961
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #4 Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs