| Assessment Year | 1991 |
|---|---|
| Principal Product | CUSTOM BINDERS |
| NAICS |
n/a
|
| SIC | 2782: Blankbooks, Looseleaf Binders and Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $208,124 | 2,645,662 |
kWh
|
$0.079 |
| Other Energy | $94,232 | 14,284 |
MMBtu
|
$6.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,001 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,001 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #4 Savings | Other Energy Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,259 | $13,297 |
$4,259
54,220
kWh
|
- | - | |
| 02 | 2.6232: Install set-back timers | $2,448 | $161 |
$2,448
31,067
kWh
|
- | - | |
| 03 | 2.7261: Install timers and/or thermostats | $7,115 | $4,000 | - | - |
$7,115
-
MMBtu
|
|
| 04 | 2.1392: Replace purchased steam with other energy source | $15,928 | - | - |
$(-78,304.0)
-
MMBtu
|
$94,232
-
MMBtu
|
|
| 05 | 2.6241: Reduce temperature of process equipment when on standby | $614 | $897 | - | - |
$614
-
MMBtu
|
|
| 06 | 2.6231: Utilize controls to operate equipment only when needed | $1,637 | - |
$1,637
20,809
kWh
|
- | - | |
| TOTAL RECOMMENDED | $32,001 | $18,355 |
$8,344
106,096
kWh
|
$(-78,304.0)
-
MMBtu
|
$101,961
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $32,001 | $18,355 |
$8,344
106,096
kWh
|
$(-78,304.0)
-
MMBtu
|
$101,961
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #4 Savings | Other Energy Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs