ITAC Assessment: MA0169
ITAC logo
ITAC Assessment: MA0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product ITALIAN DRY SAUSAGE
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $50
M
to 100
M
# of Employees 230
Plant Area
n/a
Annual Production 20,000,000
lb
Production Hrs. Annual 4,420
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $452,833 6,774,619
kWh
Natural Gas $91,409 18,250
MMBtu
Fuel Oil #2 $74,057 18,575
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,492 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,900

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.4133: Use most efficient type of electric motors $1,187 $1,752 $1,187
17,878
kWh
- -
02 2.4221: Install compressor air intakes in coolest locations $582 $740 $582
8,792
kWh
- -
03 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,087 - - $394
-
MMBtu
$693
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $231 - $231
3,517
kWh
- -
05 2.7261: Install timers and/or thermostats $405 - $200
2,931
kWh
- $205
-
MMBtu
TOTAL RECOMMENDED $3,492 $2,492 $2,200
33,118
kWh
$394
-
MMBtu
$898
-
MMBtu
TOTAL IMPLEMENTED $1,900 $740 $813
12,309
kWh
$394
-
MMBtu
$693
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs