ITAC Assessment: MA0162
ITAC logo
ITAC Assessment: MA0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product HARDWARE
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,250
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $340,151 4,837,925
kWh
Natural Gas $13,015 2,367
MMBtu
Fuel Oil #6 $97,164 34,504
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,182 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $936

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings
01 2.3191: Use demand controller or load shedder $936 $75 $936
-
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $665 $50 $665
9,379
kWh
-
03 2.3312: Install efficient rectifiers $14,209 $8,500 $14,209
202,227
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,765 $400 $1,765
25,205
kWh
-
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $636 $1,041 - $636
-
MMBtu
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,259 $14,920 $5,254
74,736
kWh
$3,005
-
MMBtu
07 2.6232: Install set-back timers $712 $150 $712
10,258
kWh
-
TOTAL RECOMMENDED $27,182 $25,136 $23,541
321,805
kWh
$3,641
-
MMBtu
TOTAL IMPLEMENTED $936 $75 $936
-
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #6 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs