ITAC Assessment: MA0127
ITAC logo
ITAC Assessment: MA0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product DECORATIVE WALL COVERING
NAICS
n/a
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 166
Plant Area
n/a
Annual Production 72,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $403,815 5,585,873
kWh
Natural Gas $263,326 54,978
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,963 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,377

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,207 $2,710 $1,207
18,171
kWh
- -
02 2.4221: Install compressor air intakes in coolest locations $3,242 $386 $3,242
44,842
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $38,184 $11,762 $38,184
528,136
kWh
- -
04 2.6232: Install set-back timers $325 $446 $325
4,396
kWh
- -
05 2.2122: Install / repair insulation on condensate lines $872 $240 - $872
-
MMBtu
-
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $21,158 - $21,958
-
kWh
- $(-800.0)
07 2.7111: Reduce illumination to minimum necessary levels $170 - $170
2,345
kWh
- -
08 2.2443: Re-use or recycle hot or cold process exhaust air $26,805 $31,196 - $26,805
-
MMBtu
-
TOTAL RECOMMENDED $91,963 $46,740 $65,086
597,890
kWh
$27,677
-
MMBtu
$(-800.0)
TOTAL IMPLEMENTED $1,377 $2,710 $1,377
20,516
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs