ITAC Assessment: MA0089
ITAC logo
ITAC Assessment: MA0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product QUARTZ TUBING
NAICS
n/a
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area
n/a
Annual Production 755,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $377,408 5,252,931
kWh
Natural Gas $26,300 4,381
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2515: Use optimum thickness insulation $1,400 $96 $1,400
19,343
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $255 $52 $255
3,517
kWh
-
03 2.6232: Install set-back timers $1,624 $500 $1,624
22,567
kWh
-
04 2.2511: Insulate bare equipment $212 $63 - $212
-
MMBtu
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,980 $1,150 $2,987
41,618
kWh
$(-1,007.0)
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $1,483 $250 $1,483
20,809
kWh
-
07 2.1221: Replace obsolete burners with more efficient ones $654 $180 - $654
-
MMBtu
08 2.2443: Re-use or recycle hot or cold process exhaust air $857 $4,290 $(-188.0)
(-2,638)
kWh
$1,045
-
MMBtu
TOTAL RECOMMENDED $8,465 $6,581 $7,561
105,216
kWh
$904
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs