ITAC Assessment: MA0001
ITAC logo
ITAC Assessment: MA0001
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product TINSEL & SPECIALTY WIRE
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $207,279 2,793,669
kWh
Fuel Oil #6 $72,515 15,215
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,982 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,982

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Fuel Oil #6 Savings
01 2.2113: Repair or replace steam traps $1,657 $30 $1,657
-
MMBtu
02 2.7442: Keep doors and windows shut when not on use $3,057 $2,345 $3,057
-
MMBtu
03 2.7261: Install timers and/or thermostats $11,268 $22,400 $11,268
-
MMBtu
TOTAL RECOMMENDED $15,982 $24,775 $15,982
-
MMBtu
TOTAL IMPLEMENTED $15,982 $24,775 $15,982
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs