ITAC Assessment: LT0066
ITAC logo
ITAC Assessment: LT0066
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product TELEPHONE CABLE
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 195
Plant Area
n/a
Annual Production 8,500,000
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $526,158 10,494,725
kWh
Natural Gas $36,514 8,495
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,753 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,230

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6232: Install set-back timers $602 $210 $602
25,205
kWh
02 2.3191: Use demand controller or load shedder $9,230 $12,000 $9,230
-
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $837 $334 $837
12,309
kWh
04 2.7441: Replace broken windows and/or window sash $84 $8 $84
3,517
kWh
TOTAL RECOMMENDED $10,753 $12,552 $10,753
41,031
kWh
TOTAL IMPLEMENTED $9,230 $12,000 $9,230
-
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs