| Assessment Year | 2026 |
|---|---|
| Principal Product | Ships |
| NAICS | 336611: Ship Building and Repairing |
| SIC | 3731: Ship Building and Repairing |
| Sales Range | $50 M to 100M |
| # of Employees | 210 |
| Plant Area |
157,496
ft2
|
| Annual Production | 15
units
|
| Production Hrs. Annual | 2,860
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $226,134 | 2,289,412 |
kWh
|
$0.099 |
| Electricity Demand | $28,551 | 9,517 |
kW-mo/yr
|
$3.00 |
| TOTAL YEARLY COSTS | $254,685 | |||
| RECOMMENDED SAVINGS* | $34,308 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $11,021 | $25 |
$11,021
111,325
kWh
|
- | |
| 02 | 2.7211: Clean and maintain refrigerant condensers and towers | $4,213 | $415 |
$4,213
42,555
kWh
|
- | |
| 03 | 2.8117: Install sub-metering equipment | $6,800 | $3,750 |
$6,800
68,682
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,269 | $2,238 |
$2,014
20,340
kWh
|
$255
-
kW-mo/yr
|
|
| 05 | 2.4224: Upgrade controls on compressors | $2,666 | $12,500 |
$2,666
26,930
kWh
|
- | |
| 06 | 2.7232: Replace existing hvac unit with high efficiency model | $680 | $3,830 |
$680
6,864
kWh
|
- | |
| 07 | 2.4226: Use / purchase optimum sized compressor | $6,659 | $43,000 |
$6,659
67,259
kWh
|
- | |
| TOTAL RECOMMENDED | $34,308 | $65,758 |
$34,053
343,955
kWh
|
$255
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs