Assessment Year | 2025 |
---|---|
Principal Product | Ship Building |
NAICS | 336611: Ship Building and Repairing |
SIC | 3731: Ship Building and Repairing |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
751,528
ft2
|
Annual Production | 10
units
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $797,867 | 9,758,000 |
kWh
|
$0.082 |
Electricity Demand | $147,789 | 32,842 |
kW-mo/yr
|
$4.50 |
TOTAL YEARLY COSTS | $945,656 | |||
RECOMMENDED SAVINGS* | $251,433 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,511 | $40 |
$3,511
42,811
kWh
|
- | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $58,573 | $1,218 |
$58,573
714,299
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $172,248 | $79,397 |
$156,516
1,908,279
kWh
|
$15,732
-
kW-mo/yr
|
|
04 | 2.4224: Upgrade controls on compressors | $17,101 | $12,500 |
$17,101
208,546
kWh
|
- | |
TOTAL RECOMMENDED | $251,433 | $93,155 |
$235,701
2,873,935
kWh
|
$15,732
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs