ITAC Assessment: LS2503
ITAC logo
ITAC Assessment: LS2503
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Ship Building
NAICS 336611: Ship Building and Repairing
SIC 3731: Ship Building and Repairing
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 751,528
ft2
Annual Production 10
units
Production Hrs. Annual 6,552
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $797,867 9,758,000
kWh
Electricity Demand $147,789 32,842
kW-mo/yr
TOTAL YEARLY COSTS $945,656
RECOMMENDED SAVINGS* $251,433 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7261: Install timers and/or thermostats $3,511 $40 $3,511
42,811
kWh
-
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $58,573 $1,218 $58,573
714,299
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $172,248 $79,397 $156,516
1,908,279
kWh
$15,732
-
kW-mo/yr
04 2.4224: Upgrade controls on compressors $17,101 $12,500 $17,101
208,546
kWh
-
TOTAL RECOMMENDED $251,433 $93,155 $235,701
2,873,935
kWh
$15,732
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs