ITAC Assessment: LS1914
ITAC logo
ITAC Assessment: LS1914
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Fabricated Pipe
NAICS 332996: Fabricated Pipe and Pipe Fitting Manufacturing
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 80,000
ft2
Annual Production 57,900
units
Production Hrs. Annual 2,600
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,047 1,288,077
kWh
Electricity Demand $47,663 7,144
kW-mo/yr
Waste Disposal Costs
Water Usage $1,828 925
Tgal
TOTAL YEARLY COSTS $149,538
RECOMMENDED SAVINGS* $15,007 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,645

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6231: Utilize controls to operate equipment only when needed $3,599 $164 $3,599
46,333
kWh
-
02 2.6218: Turn off equipment when not in use $588 - $588
7,574
kWh
-
03 2.7134: Use photocell controls $294 $226 $294
3,791
kWh
-
04 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $164 $90 $164
2,118
kWh
-
05 2.7135: Install occupancy sensors $168 $135 $168
2,163
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $10,194 $22,875 $7,300
93,990
kWh
$2,894
-
kW-mo/yr
TOTAL RECOMMENDED $15,007 $23,490 $12,113
155,969
kWh
$2,894
-
kW-mo/yr
TOTAL IMPLEMENTED $4,645 $480 $4,645
59,816
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs