ITAC Assessment: BD0482
ITAC logo
ITAC Assessment: BD0482
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Planter assembly discs
NAICS 332216: Saw Blade and Handtool Manufacturing
SIC 3523: Farm Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 34
Plant Area 38,145
ft2
Annual Production 789,900
pieces
Production Hrs. Annual 3,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,552 806,567
kWh
Electricity Demand $17,842 2,212
kW-mo/yr
Electricity Fees $768 -
Natural Gas $46,241 9,034
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $195,604 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $190,052

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,155 $9,455 $3,228
59,767
kWh
$927
-
kW-mo/yr
- - - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,096 $840 $1,628
30,139
kWh
$468
-
kW-mo/yr
- - - -
03 2.2442: Preheat combustion air with waste heat $1,149 $2,000 $(-503.0)
(-9,310)
kWh
$(-144.0)
-
kW-mo/yr
$1,796
-
MMBtu
- - -
04 2.7135: Install occupancy sensors $738 $825 $488
9,027
kWh
$250
-
kW-mo/yr
- - - -
05 2.4133: Use most efficient type of electric motors $507 $600 $378
6,996
kWh
$129
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $152 $184 $72
1,332
kWh
$14
-
kW-mo/yr
- $29 - $37
07 3.2121: Convert to electrostatic powder coating $186,807 $160,000 - - $(-3,609.0)
-
MMBtu
- $190,416 -
TOTAL RECOMMENDED $195,604 $173,904 $5,291
97,951
kWh
$1,644
-
kW-mo/yr
$(-1,813.0)
-
MMBtu
$29 $190,416 $37
TOTAL IMPLEMENTED $190,052 $162,840 $1,125
20,829
kWh
$324
-
kW-mo/yr
$(-1,813.0)
-
MMBtu
- $190,416 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs