| Assessment Year | 2026 |
|---|---|
| Principal Product | Plastic Foam |
| NAICS | 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing |
| SIC | 3086: Plastics Foam Products |
| Sales Range | $100 M to 500M |
| # of Employees | 63 |
| Plant Area |
178,800
ft2
|
| Annual Production | 468,255
units
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $383,826 | 3,274,622 |
kWh
|
$0.12 |
| Electricity Demand | $45,543 | 17,625 |
kW-mo/yr
|
$2.58 |
| Electricity Fees | $(-704.0) | - |
|
- |
| Natural Gas | $68,800 | 12,938 |
MMBtu
|
$5.32 |
| TOTAL YEARLY COSTS | $497,465 | |||
| RECOMMENDED SAVINGS* | $45,642 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,693 | - |
$2,551
21,622
kWh
|
$142
-
kW-mo/yr
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $9,619 | - |
$1,627
13,903
kWh
|
- |
$7,992
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,628 | $2,200 |
$19,364
165,496
kWh
|
$1,264
-
kW-mo/yr
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $5,352 | $4,000 |
$5,213
44,554
kWh
|
$139
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,119 | $5,034 |
$1,913
15,940
kWh
|
$206
-
kW-mo/yr
|
- | |
| 06 | 2.2442: Preheat combustion air with waste heat | $1,620 | $7,750 |
$(-454.0)
(-3,879)
kWh
|
$(-46.0)
-
kW-mo/yr
|
$2,120
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $712 | $3,905 |
$629
5,375
kWh
|
$83
-
kW-mo/yr
|
- | |
| 08 | 2.7233: Use properly designed and sized hvac equipment | $2,899 | $19,500 | - | - |
$2,899
-
MMBtu
|
|
| TOTAL RECOMMENDED | $45,642 | $42,389 |
$30,843
263,011
kWh
|
$1,788
-
kW-mo/yr
|
$13,011
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs