| Assessment Year | 2026 |
|---|---|
| Principal Product | Medical spray and valve system |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 147 |
| Plant Area |
160,000
ft2
|
| Annual Production | 1,200,000
units
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $801,189 | 18,244,812 |
kWh
|
$0.044 | |
| Electricity Demand | $299,502 | 33,798 |
kW-mo/yr
|
$8.86 | |
| Electricity Fees | $9,692 | - |
|
- | |
| Natural Gas | $82,169 | 6,745 |
MMBtu
|
$12.18 | |
| Waste Disposal Costs | |||||
| Water Usage | $34,639 | 3,065 |
Tgal
|
$11.30 | |
| TOTAL YEARLY COSTS | $1,227,191 | ||||
| RECOMMENDED SAVINGS* | $50,075 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,594 | - |
$3,602
81,856
kWh
|
$992
-
kW-mo/yr
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $8,437 | $240 |
$2,830
64,311
kWh
|
- |
$5,607
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $6,951 | $2,190 |
$6,062
137,779
kWh
|
- |
$889
-
MMBtu
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $3,974 | $4,000 |
$3,575
81,245
kWh
|
$399
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $135 | $140 |
$135
3,066
kWh
|
- | - | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $23,604 | $65,464 |
$18,501
420,480
kWh
|
$5,103
-
kW-mo/yr
|
- | |
| 07 | 2.2442: Preheat combustion air with waste heat | $2,380 | $10,000 |
$(-645.0)
(-14,663)
kWh
|
$(-239.0)
-
kW-mo/yr
|
$3,264
-
MMBtu
|
|
| TOTAL RECOMMENDED | $50,075 | $82,034 |
$34,060
774,074
kWh
|
$6,255
-
kW-mo/yr
|
$9,760
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs