ITAC Assessment: LE0594
ITAC logo
ITAC Assessment: LE0594
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product coated metal parts
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 30,000
ft2
Annual Production 240,000
pieces
Production Hrs. Annual 4,335
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,550 737,888
kWh
Electricity Demand $9,046 3,219
kW-mo/yr
Electricity Fees $4,569 -
LPG $112,753 10,087
MMBtu
Waste Disposal Costs
Water Usage $2,068 213
Tgal
TOTAL YEARLY COSTS $186,986
RECOMMENDED SAVINGS* $87,898 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings One-time Revenue or Avoided Cost Savings
01 2.7261: Install timers and/or thermostats $3,456 - - - $3,456
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,393 $1,560 $4,910
62,150
kWh
$483
-
kW-mo/yr
- -
03 2.2443: Re-use or recycle hot or cold process exhaust air $2,962 $2,500 - - $2,962
-
MMBtu
-
04 3.4111: Use closed cycle process to minimize waste water production $42,706 $75,000 - - - $42,706
05 2.7232: Replace existing hvac unit with high efficiency model $8,003 $22,000 - - $8,003
-
MMBtu
-
06 2.4226: Use / purchase optimum sized compressor $5,643 $16,923 $5,137
65,025
kWh
$506
-
kW-mo/yr
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,206 $17,020 $3,666
45,350
kWh
$540
-
kW-mo/yr
- -
08 2.3192: Use fossil fuel powered generator during peak demand periods $15,529 $74,000 - - - $15,529
TOTAL RECOMMENDED $87,898 $209,003 $13,713
172,525
kWh
$1,529
-
kW-mo/yr
$14,421
-
MMBtu
$58,235
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs