Assessment Year | 2025 |
---|---|
Principal Product | coated metal parts |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
30,000
ft2
|
Annual Production | 240,000
pieces
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $58,550 | 737,888 |
kWh
|
$0.079 | |
Electricity Demand | $9,046 | 3,219 |
kW-mo/yr
|
$2.81 | |
Electricity Fees | $4,569 | - |
|
- | |
LPG | $112,753 | 10,087 |
MMBtu
|
$11.18 | |
Waste Disposal Costs | |||||
Water Usage | $2,068 | 213 |
Tgal
|
$9.71 | |
TOTAL YEARLY COSTS | $186,986 | ||||
RECOMMENDED SAVINGS* | $87,898 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,456 | - | - | - |
$3,456
-
MMBtu
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,393 | $1,560 |
$4,910
62,150
kWh
|
$483
-
kW-mo/yr
|
- | - | |
03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $2,962 | $2,500 | - | - |
$2,962
-
MMBtu
|
- | |
04 | 3.4111: Use closed cycle process to minimize waste water production | $42,706 | $75,000 | - | - | - | $42,706 | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $8,003 | $22,000 | - | - |
$8,003
-
MMBtu
|
- | |
06 | 2.4226: Use / purchase optimum sized compressor | $5,643 | $16,923 |
$5,137
65,025
kWh
|
$506
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,206 | $17,020 |
$3,666
45,350
kWh
|
$540
-
kW-mo/yr
|
- | - | |
08 | 2.3192: Use fossil fuel powered generator during peak demand periods | $15,529 | $74,000 | - | - | - | $15,529 | |
TOTAL RECOMMENDED | $87,898 | $209,003 |
$13,713
172,525
kWh
|
$1,529
-
kW-mo/yr
|
$14,421
-
MMBtu
|
$58,235 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs