Assessment Year | 2024 |
---|---|
Principal Product | electronic connectors |
NAICS | 335931: Current-Carrying Wiring Device Manufacturing |
SIC | 3678: Electronic Connectors |
Sales Range | $100 M to 500M |
# of Employees | 239 |
Plant Area |
108,000
ft2
|
Annual Production | 310,433
units
|
Production Hrs. Annual | 4,212
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $344,582 | 6,248,000 |
kWh
|
$0.055 |
Electricity Demand | $97,436 | 18,912 |
kW-mo/yr
|
$5.15 |
Electricity Fees | $56,795 | - |
|
- |
Natural Gas | $18,544 | 1,784 |
MMBtu
|
$10.39 |
TOTAL YEARLY COSTS | $517,357 | |||
RECOMMENDED SAVINGS* | $426,075 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $8,432 | - |
$5,637
102,488
kWh
|
- |
$2,795
-
MMBtu
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,203 | - |
$2,467
44,863
kWh
|
$736
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $486 | $75 |
$486
8,829
kWh
|
- | - | - | |
04 | 2.2443: Re-use or recycle hot or cold process exhaust air | $14,556 | $2,500 | - | - |
$14,556
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,123 | $560 |
$2,604
47,349
kWh
|
$519
-
kW-mo/yr
|
- | - | |
06 | 2.2443: Re-use or recycle hot or cold process exhaust air | $8,208 | $2,500 | - | - |
$8,208
-
MMBtu
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $3,633 | $4,000 |
$3,303
60,060
kWh
|
$330
-
kW-mo/yr
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,069 | $4,000 |
$1,858
33,779
kWh
|
$211
-
kW-mo/yr
|
- | - | |
09 | 2.7232: Replace existing hvac unit with high efficiency model | $17,682 | $55,039 |
$16,817
305,760
kWh
|
$865
-
kW-mo/yr
|
- | - | |
10 | 2.9114: Use solar heat to make electricty | $54,887 | $613,200 |
$31,767
577,586
kWh
|
- | - | $23,120 | |
11 | 2.9114: Use solar heat to make electricty | $309,796 | $3,462,200 |
$179,356
3,261,024
kWh
|
- | - | $130,440 | |
TOTAL RECOMMENDED | $426,075 | $4,144,074 |
$244,295
4,441,738
kWh
|
$2,661
-
kW-mo/yr
|
$25,559
-
MMBtu
|
$153,560 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs