ITAC Assessment: LE0575
ITAC logo
ITAC Assessment: LE0575
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Bottled Water
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 325,000
ft2
Annual Production 650,000,000
units
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,130,237 76,848,500
kWh
Electricity Demand $379,130 120,969
kW-mo/yr
Electricity Fees $282,163 -
Natural Gas $91,198 7,397
MMBtu
Waste Disposal Costs
Water Usage $885,970 324,685
Tgal
Water Disposal $374,079 76,014
Tgal
TOTAL YEARLY COSTS $6,142,777
RECOMMENDED SAVINGS* $619,995 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $23,173 $100 $21,464
397,488
kWh
$1,709
-
kW-mo/yr
02 2.2623: Minimize condenser cooling water temperature $6,164 $100 $5,316
98,445
kWh
$848
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $45,906 $7,700 $39,602
733,369
kWh
$6,304
-
kW-mo/yr
04 2.4221: Install compressor air intakes in coolest locations $118,088 $80,000 $114,445
2,119,354
kWh
$3,643
-
kW-mo/yr
05 2.2511: Insulate bare equipment $37,603 $28,720 $37,356
691,769
kWh
$247
-
kW-mo/yr
06 2.2622: Replace existing chiller with high efficiency model $242,187 $285,000 $235,939
4,369,244
kWh
$6,248
-
kW-mo/yr
07 2.4226: Use / purchase optimum sized compressor $83,526 $121,547 $77,366
1,432,704
kWh
$6,160
-
kW-mo/yr
08 2.7261: Install timers and/or thermostats $1,618 $2,720 $1,618
29,957
kWh
-
09 2.2444: Use hot process fluids to preheat incoming process fluids $36,513 $150,000 $32,832
608,007
kWh
$3,681
-
kW-mo/yr
10 2.7232: Replace existing hvac unit with high efficiency model $25,217 $144,000 $23,705
438,984
kWh
$1,512
-
kW-mo/yr
TOTAL RECOMMENDED $619,995 $819,887 $589,643
10,919,321
kWh
$30,352
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs