ITAC Assessment: LE0537
ITAC logo
ITAC Assessment: LE0537
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product lids
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3466: Crowns and Closures
Sales Range $50
M
to 100
M
# of Employees 130
Plant Area 151,000
ft2
Annual Production 1,000,000,000
units
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $906,525 16,723,400
kWh
Electricity Demand $67,524 26,480
kW-mo/yr
Electricity Fees $63,969 -
Natural Gas $854,928 148,685
MMBtu
TOTAL YEARLY COSTS $1,892,946
RECOMMENDED SAVINGS* $302,436 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $247,075

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $167,234 - - - - $167,234
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,776 $15,000 $17,631
326,532
kWh
$1,145
-
kW-mo/yr
- -
03 2.7261: Install timers and/or thermostats $825 $570 $387
7,160
kWh
- $438
-
MMBtu
-
04 2.2443: Re-use or recycle hot or cold process exhaust air $6,501 $7,500 - - $6,501
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $6,193 $7,500 $5,816
107,689
kWh
$377
-
kW-mo/yr
- -
06 2.2442: Preheat combustion air with waste heat $23,891 $70,000 $(-3,759.0)
(-65,372)
kWh
- $27,650
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $21,096 $67,533 $19,811
366,868
kWh
$1,285
-
kW-mo/yr
- -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $57,920 $245,000 $54,156
1,002,902
kWh
$3,764
-
kW-mo/yr
- -
TOTAL RECOMMENDED $302,436 $413,103 $94,042
1,745,779
kWh
$6,571
-
kW-mo/yr
$34,589
-
MMBtu
$167,234
TOTAL IMPLEMENTED $247,075 $313,103 $74,354
1,376,930
kWh
$5,049
-
kW-mo/yr
$438
-
MMBtu
$167,234
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs