Assessment Year | 2021 |
---|---|
Principal Product | Display Boards |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
67,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 4,264
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,775 | 1,113,300 |
kWh
|
$0.065 |
Electricity Demand | $15,306 | 3,778 |
kW-mo/yr
|
$4.05 |
Electricity Fees | $16,812 | - |
|
- |
Natural Gas | $12,550 | 1,461 |
MMBtu
|
$8.59 |
TOTAL YEARLY COSTS | $117,443 | |||
RECOMMENDED SAVINGS* | $20,669 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,310 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,133 | $100 |
$1,011
15,553
kWh
|
$122
-
kW-mo/yr
|
- | |
02 | 2.7261: Install timers and/or thermostats | $985 | $100 |
$418
6,429
kWh
|
- |
$567
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $560 | $500 |
$499
7,677
kWh
|
$61
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,825 | $20,000 |
$8,574
131,902
kWh
|
$1,251
-
kW-mo/yr
|
- | |
05 | 2.7263: Lower compressor pressure through a/c system modification | $534 | $1,240 |
$453
6,966
kWh
|
$81
-
kW-mo/yr
|
- | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $7,632 | $36,000 |
$7,259
111,681
kWh
|
$373
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $20,669 | $57,940 |
$18,214
280,208
kWh
|
$1,888
-
kW-mo/yr
|
$567
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,310 | $36,700 |
$9,187
141,340
kWh
|
$556
-
kW-mo/yr
|
$567
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs