Assessment Year | 2020 |
---|---|
Principal Product | Rods and wires |
NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
Sales Range | $100 M to 500M |
# of Employees | 33 |
Plant Area |
120,000
ft2
|
Annual Production | 5,500,000
units
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $793,798 | 17,179,211 |
kWh
|
$0.046 |
Electricity Demand | $99,817 | 33,492 |
kW-mo/yr
|
$2.98 |
Electricity Fees | $30,314 | - |
|
- |
Natural Gas | $297,739 | 45,135 |
MMBtu
|
$6.60 |
TOTAL YEARLY COSTS | $1,221,668 | |||
RECOMMENDED SAVINGS* | $80,958 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,038 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,038 | $1,620 |
$741
16,103
kWh
|
- |
$2,297
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,651 | $13,000 |
$19,277
419,065
kWh
|
$1,374
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,586 | $11,000 |
$9,883
214,848
kWh
|
$703
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,225 | $8,000 |
$6,745
146,633
kWh
|
$480
-
kW-mo/yr
|
- | |
05 | 2.2442: Preheat combustion air with waste heat | $22,684 | $35,000 | - | - |
$22,684
-
MMBtu
|
|
06 | 2.4226: Use / purchase optimum sized compressor | $3,199 | $10,000 |
$2,838
61,690
kWh
|
$361
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,702 | $43,257 |
$7,528
163,655
kWh
|
$1,174
-
kW-mo/yr
|
- | |
08 | 2.7232: Replace existing hvac unit with high efficiency model | $4,873 | $27,900 |
$4,137
89,940
kWh
|
$736
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $80,958 | $149,777 |
$51,149
1,111,934
kWh
|
$4,828
-
kW-mo/yr
|
$24,981
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,038 | $1,620 |
$741
16,103
kWh
|
- |
$2,297
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs