Assessment Year | 2019 |
---|---|
Principal Product | Wastewater Equipment |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 47 |
Plant Area |
120,000
ft2
|
Annual Production | 20,000
units
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,227 | 1,293,130 |
kWh
|
$0.084 |
Electricity Demand | $36,394 | 5,647 |
kW-mo/yr
|
$6.44 |
Electricity Fees | $24,291 | - |
|
- |
LPG | $49,403 | 2,396 |
MMBtu
|
$20.62 |
Fuel Oil #2 | $117,941 | 7,530 |
MMBtu
|
$15.66 |
TOTAL YEARLY COSTS | $336,256 | |||
RECOMMENDED SAVINGS* | $133,657 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $133,657 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $7,603 | - |
$1,026
12,213
kWh
|
- |
$6,577
-
MMBtu
|
- | |
02 | 2.2437: Recover waste heat from equipment | $5,873 | $6,000 | - | - |
$5,873
-
MMBtu
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,670 | $2,500 |
$1,290
15,355
kWh
|
$380
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,910 | $23,990 |
$9,508
113,183
kWh
|
$2,402
-
kW-mo/yr
|
- | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $1,805 | $5,500 |
$1,393
16,579
kWh
|
$412
-
kW-mo/yr
|
- | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $16,879 | $51,500 |
$13,034
155,168
kWh
|
$3,845
-
kW-mo/yr
|
- | - | |
07 | 2.1331: Burn a less expensive grade of fuel | $87,917 | $290,000 | - | - | - | $87,917 | |
TOTAL RECOMMENDED | $133,657 | $379,490 |
$26,251
312,498
kWh
|
$7,039
-
kW-mo/yr
|
$12,450
-
MMBtu
|
$87,917 | ||
TOTAL IMPLEMENTED | $133,657 | $379,490 |
$26,251
312,498
kWh
|
$7,039
-
kW-mo/yr
|
$12,450
-
MMBtu
|
$87,917 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs