Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product research chemicals
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range greater than $500
M
# of Employees 600
Plant Area 850,000
ft2
Annual Production 4,119,897
pieces
Production Hrs. Annual 6,336
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $823,864 18,833,577
kWh
Electricity Demand $432,021 38,168
kW-mo/yr
Natural Gas $1,102,005 114,697
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,889 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $1,078 $642 $659
14,976
kWh
$419
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $206 - $206
4,676
kWh
- -
03 2.9112: Use solar heat to heat water $605 $2,240 - - $605
-
MMBtu
TOTAL RECOMMENDED $1,889 $2,882 $865
19,652
kWh
$419
-
kW-mo/yr
$605
-
MMBtu
TOTAL IMPLEMENTED - - - - -