ITAC Assessment: ME0205
ITAC logo
ITAC Assessment: ME0205
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Canned Sardines
NAICS
n/a
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area 37,691
ft2
Annual Production 200,000
units
Production Hrs. Annual 3,400
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,340 1,472,157
kWh
Electricity Demand $34,436 3,945
kW-mo/yr
Electricity Fees $15,565 -
Fuel Oil #6 $49,567 16,044
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $141,917 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $133,456

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
01 4.453: Reschedule breaks to allow for continuous production $115,428 - - - - $(-447,072.0) - $562,500
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,183 $7,572 $1,694
24,326
kWh
$489
-
kW-mo/yr
- - - -
03 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $1,380 $453 $990
14,068
kWh
$390
-
kW-mo/yr
- - - -
04 2.2511: Insulate bare equipment $1,004 $2,112 - - $1,004
-
MMBtu
- - -
05 2.4239: Eliminate or reduce compressed air usage $1,306 $595 $1,306
23,154
kWh
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $285 $200 $285
4,103
kWh
- - - - -
07 2.2511: Insulate bare equipment $244 $38 $183
2,638
kWh
- $61
-
MMBtu
- - -
08 2.2511: Insulate bare equipment $196 $270 $196
5,569
kWh
- - - - -
09 2.2135: Repair and eliminate steam leaks $11,040 $200 - - $10,530
-
MMBtu
- $510
-
Tgal
-
10 3.4151: Minimize water usage $2,844 $2,302 $783
11,137
kWh
$1,173
-
kW-mo/yr
$685
-
MMBtu
- $203
-
Tgal
-
11 3.4115: Recover and reuse cooling water $2,370 $2,400 - - - - $2,370
-
Tgal
-
12 3.4151: Minimize water usage $1,946 $3,800 - - - - $1,946
-
Tgal
-
13 3.4151: Minimize water usage $1,236 $75 $1,008
14,361
kWh
- - - $228
-
Tgal
-
14 3.4151: Minimize water usage $455 $415 - - - - $455
-
Tgal
-
TOTAL RECOMMENDED $141,917 $20,432 $6,445
99,356
kWh
$2,052
-
kW-mo/yr
$12,280
-
MMBtu
$(-447,072.0) $5,712
-
Tgal
$562,500
TOTAL IMPLEMENTED $133,456 $10,657 $4,149
62,134
kWh
$1,662
-
kW-mo/yr
$11,276
-
MMBtu
$(-447,072.0) $941
-
Tgal
$562,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs