| Assessment Year | 1996 |
|---|---|
| Principal Product | Canned Sardines |
| NAICS |
n/a
|
| SIC | 2091: Canned and Cured Fish and Seafoods |
| Sales Range | $5 M to 10M |
| # of Employees | 150 |
| Plant Area |
37,691
ft2
|
| Annual Production | 200,000
units
|
| Production Hrs. Annual | 3,400
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $100,340 | 1,472,157 |
kWh
|
$0.068 |
| Electricity Demand | $34,436 | 3,945 |
kW-mo/yr
|
$8.73 |
| Electricity Fees | $15,565 | - |
|
- |
| Fuel Oil #6 | $49,567 | 16,044 |
MMBtu
|
$3.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $141,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $133,456 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Personnel Changes Savings | Water Consumption Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.453: Reschedule breaks to allow for continuous production | $115,428 | - | - | - | - | $(-447,072.0) | - | $562,500 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,183 | $7,572 |
$1,694
24,326
kWh
|
$489
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,380 | $453 |
$990
14,068
kWh
|
$390
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,004 | $2,112 | - | - |
$1,004
-
MMBtu
|
- | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $1,306 | $595 |
$1,306
23,154
kWh
|
- | - | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $285 | $200 |
$285
4,103
kWh
|
- | - | - | - | - | |
| 07 | 2.2511: Insulate bare equipment | $244 | $38 |
$183
2,638
kWh
|
- |
$61
-
MMBtu
|
- | - | - | |
| 08 | 2.2511: Insulate bare equipment | $196 | $270 |
$196
5,569
kWh
|
- | - | - | - | - | |
| 09 | 2.2135: Repair and eliminate steam leaks | $11,040 | $200 | - | - |
$10,530
-
MMBtu
|
- |
$510
-
Tgal
|
- | |
| 10 | 3.4151: Minimize water usage | $2,844 | $2,302 |
$783
11,137
kWh
|
$1,173
-
kW-mo/yr
|
$685
-
MMBtu
|
- |
$203
-
Tgal
|
- | |
| 11 | 3.4115: Recover and reuse cooling water | $2,370 | $2,400 | - | - | - | - |
$2,370
-
Tgal
|
- | |
| 12 | 3.4151: Minimize water usage | $1,946 | $3,800 | - | - | - | - |
$1,946
-
Tgal
|
- | |
| 13 | 3.4151: Minimize water usage | $1,236 | $75 |
$1,008
14,361
kWh
|
- | - | - |
$228
-
Tgal
|
- | |
| 14 | 3.4151: Minimize water usage | $455 | $415 | - | - | - | - |
$455
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $141,917 | $20,432 |
$6,445
99,356
kWh
|
$2,052
-
kW-mo/yr
|
$12,280
-
MMBtu
|
$(-447,072.0) |
$5,712
-
Tgal
|
$562,500 | ||
| TOTAL IMPLEMENTED | $133,456 | $10,657 |
$4,149
62,134
kWh
|
$1,662
-
kW-mo/yr
|
$11,276
-
MMBtu
|
$(-447,072.0) |
$941
-
Tgal
|
$562,500 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Personnel Changes Savings | Water Consumption Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs