Assessment Year | 2019 |
---|---|
Principal Product | syringe components |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 330 |
Plant Area |
130,000
ft2
|
Annual Production | 250,000,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,471,568 | 23,801,800 |
kWh
|
$0.062 |
Natural Gas | $237,916 | 56,240 |
MMBtu
|
$4.23 |
TOTAL YEARLY COSTS | $1,709,484 | |||
RECOMMENDED SAVINGS* | $107,511 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,669 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,428 | $1,040 |
$7,428
119,812
kWh
|
- | - | |
02 | 2.2113: Repair or replace steam traps | $14,878 | $3,810 | - |
$14,878
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $215 | $70 |
$215
3,469
kWh
|
- | - | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $35,019 | $27,273 |
$35,019
564,812
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $743 | $2,613 |
$743
11,987
kWh
|
- | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $3,620 | $18,280 |
$3,620
58,382
kWh
|
- | - | |
07 | 2.1224: Replace boiler | $45,608 | $325,000 | - |
$40,608
-
MMBtu
|
$5,000 | |
TOTAL RECOMMENDED | $107,511 | $378,086 |
$47,025
758,462
kWh
|
$55,486
-
MMBtu
|
$5,000 | ||
TOTAL IMPLEMENTED | $26,669 | $25,743 |
$11,791
190,181
kWh
|
$14,878
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs