Assessment Year | 2013 |
---|---|
Principal Product | Air Filtration Systems |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 125 |
Plant Area |
280,000
ft2
|
Annual Production | 4,200
units
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $231,508 | 5,287,563 |
kWh
|
$0.044 |
Electricity Demand | $58,406 | 13,125 |
kW-mo/yr
|
$4.45 |
Natural Gas | $131,279 | 20,508 |
MMBtu
|
$6.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,281 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,733 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $2,733 | - | - | - | $2,733 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,745 | $52,650 |
$11,600
264,870
kWh
|
$3,145
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $3,000 | $2,520 |
$3,000
68,580
kWh
|
- | - | |
04 | 2.3132: Recharge batteries on during off-peak demand periods | $600 | - | - |
$600
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,426 | $53,400 |
$10,565
241,200
kWh
|
$2,861
-
kW-mo/yr
|
- | |
06 | 2.4323: Use optimum size and capacity equipment | $2,177 | $8,000 |
$1,790
40,874
kWh
|
$387
-
kW-mo/yr
|
- | |
07 | 2.4323: Use optimum size and capacity equipment | $7,599 | $12,000 |
$6,095
139,163
kWh
|
$1,504
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $44,281 | $128,570 |
$33,050
754,687
kWh
|
$8,498
-
kW-mo/yr
|
$2,733 | ||
TOTAL IMPLEMENTED | $5,733 | $2,520 |
$3,000
68,580
kWh
|
- | $2,733 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs