Assessment Year | 2019 |
---|---|
Principal Product | Zinc Die Casting |
NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
SIC | 3364: Nonferrous Die-Castings, Except Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
50,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $168,089 | 1,606,336 |
kWh
|
$0.10 |
Electricity Demand | $61,260 | 7,006 |
kW-mo/yr
|
$8.74 |
Electricity Fees | $7,204 | - |
|
- |
Natural Gas | $161,814 | 19,022 |
MMBtu
|
$8.51 |
TOTAL YEARLY COSTS | $398,367 | |||
RECOMMENDED SAVINGS* | $78,506 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,883 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $825 | $70 |
$272
2,592
kWh
|
- |
$553
-
MMBtu
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $40,407 | $37,000 |
$33,896
322,820
kWh
|
$6,511
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,990 | $2,000 |
$1,789
17,038
kWh
|
$201
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,116 | $6,000 |
$2,644
25,178
kWh
|
$472
-
kW-mo/yr
|
- | - | |
05 | 2.7233: Use properly designed and sized hvac equipment | $14,748 | $50,000 | - | - |
$14,748
-
MMBtu
|
- | |
06 | 2.2442: Preheat combustion air with waste heat | $9,352 | $35,000 | - | - |
$9,352
-
MMBtu
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,568 | $30,054 |
$6,432
61,256
kWh
|
$1,136
-
kW-mo/yr
|
- | - | |
08 | 2.4321: Upgrade obsolete equipment | $500 | $5,000 | - | - | - | $500 | |
TOTAL RECOMMENDED | $78,506 | $165,124 |
$45,033
428,884
kWh
|
$8,320
-
kW-mo/yr
|
$24,653
-
MMBtu
|
$500 | ||
TOTAL IMPLEMENTED | $10,883 | $37,124 |
$8,493
80,886
kWh
|
$1,337
-
kW-mo/yr
|
$553
-
MMBtu
|
$500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs