ITAC Assessment: LE0434
ITAC logo
ITAC Assessment: LE0434
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Corrugated Boxes
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 23
Plant Area 67,461
ft2
Annual Production 1,000,000
units
Production Hrs. Annual 4,992
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,053 2,002,600
kWh
Electricity Demand $23,407 7,265
kW-mo/yr
Electricity Fees $5,640 -
Natural Gas $47,269 5,908
MMBtu
TOTAL YEARLY COSTS $232,369
RECOMMENDED SAVINGS* $46,006 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,827

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $1,784 $28 $48
620
kWh
- $1,736
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,031 $1,000 $2,757
35,347
kWh
$274
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $2,560 $1,080 - - $2,560
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $576 $300 $521
6,682
kWh
$55
-
kW-mo/yr
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $25,921 $65,000 $23,580
302,303
kWh
$2,341
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,129 $5,350 $2,129
27,300
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $483 $1,450 $406
5,200
kWh
$77
-
kW-mo/yr
-
08 2.4226: Use / purchase optimum sized compressor $9,523 $40,000 $8,663
111,064
kWh
$860
-
kW-mo/yr
-
TOTAL RECOMMENDED $46,006 $114,208 $38,104
488,516
kWh
$3,606
-
kW-mo/yr
$4,296
-
MMBtu
TOTAL IMPLEMENTED $4,827 $2,558 $454
5,820
kWh
$77
-
kW-mo/yr
$4,296
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs